What is a goods received note?
A goods received note is your factory's own record that supplier material has arrived. Stores makes it at the receiving site, after counting and checking the material.
It does three jobs. It adds the accepted quantity to stock. It tells accounts what to pay. And it builds a record of how each supplier delivers.
A GRN is not a purchase order. The PO is what you asked for. The GRN is what actually came in, and what you kept.
The GRN number is the unique number on each note. Keep one running series per site, and never reuse a number.
GRN vs delivery challan vs purchase order vs invoice
Four papers travel with every purchase, and each proves something different. For the outward side, see our guide on delivery challan vs invoice.
| Document | Who makes it | When | What it proves |
|---|---|---|---|
| Purchase order | You (purchase) | Before the supplier ships | What you ordered, at what rate |
| Delivery challan | Supplier | Travels with the goods | What the supplier says it sent |
| Tax invoice | Supplier | With or before the goods | What the supplier bills, with GST |
| Goods received note | You (stores) | After counting and checking | What arrived and what you accepted |
What each column in the GRN format means
The template has three parts: header fields, item lines and sign-off.
Header fields
- GRN no.: the next number in your running series. Never skip or reuse one.
- GRN date: the day the material reached you, not the day you typed it.
- Receiving store or site: where it was unloaded, if you have more than one store.
- Supplier name and GSTIN: copy the GSTIN from the invoice and check it matches the PO.
- PO no. and date: the order this delivery belongs to.
- Supplier invoice or challan no. and date: from the paper that came with the vehicle.
- E-way bill no.: from the supplier's e-way bill, so your papers match theirs.
- Vehicle no. and transporter or LR no.: helps you trace a short or damaged delivery.
Item columns
- Item (with code): as on your PO, with your item code, not the supplier's name for it.
- HSN: from the invoice. It should match your PO and item master.
- Unit: kg, nos, metres or litres. Use the same unit as the PO.
- PO qty: what you ordered on this line.
- Invoice/challan qty: what the supplier says it sent.
- Received qty: what you counted or weighed. Never copy the invoice figure.
- Accepted qty: what passed your check and goes into stock.
- Rejected qty: what failed your check. Write 0 if nothing was rejected.
- Reason/remark: one short reason, such as "rusted". Note shortages and part deliveries here too.
- Batch/heat no.: for material you must trace later, like steel heats or chemical batches.
- Rate ex-GST: the PO rate in ₹, before GST.
- Accepted value (₹): accepted qty × rate. This is what accounts pays, before GST.
A quick check on every line: accepted plus rejected must equal received. If it doesn't, someone miscounted.
Sign-off
Leave four boxes at the bottom: received by (stores), inspected by, approved by, and accounts. Each person signs and dates the note.
How to fill a GRN, step by step
Fill the GRN at the gate, on the day the truck arrives.
[[IMAGE {"type":"steps","title":"How to fill a GRN at the gate","items":["Match invoice and e-way bill to vehicle","Count or weigh; write your own figure","Check item and quantity against the PO","Inspect, then split accepted and rejected","Sign, update stock, send to accounts"]}]]
Yes, you can run all of this in Excel; download the template above. Making the parts list as well? Use our bill of materials format.
Worked example: steel and hardware received at a fabrication unit
A fabrication unit ordered steel and fasteners on one PO. One truck arrived with one invoice. All numbers below are illustrative.
Table 1 (Example): GRN header
| Field | Example value |
|---|---|
| GRN no. and date | GRN/26-27/0418, 12 Nov 2026 |
| Receiving store | Main store |
| Supplier name and GSTIN | Example Steel Traders, 27AAAAA0000A1Z5 |
| PO no. and date | PO/26-27/0392, 3 Nov 2026 |
| Supplier invoice no. and date | EST/1187, 11 Nov 2026 |
| E-way bill no. | 1612 3456 7890 |
| Vehicle no. and LR no. | MH 12 AB 1234, LR 5521 |
Table 2 (Example): item lines
| Item | Invoice qty | Received / accepted / rejected | Remark |
|---|---|---|---|
| MS plate 10 mm (kg) | 2,000 | 1,985 / 1,985 / 0 | Short 15 kg on weighbridge |
| MS angle 50×50×5 (kg) | 1,500 | 1,500 / 1,440 / 60 | 60 kg bent, returned |
| Hex bolt M12×50 (nos) | 3,000 of 5,000 ordered | 3,000 / 3,000 / 0 | Part delivery, 2,000 pending |
| Plain washer M12 (nos) | 5,000 | 5,000 / 4,900 / 100 | 100 rusted, returned |
Table 3 (Example): what accounts pays and what goes back
| Line | Invoice value (₹) | Accepted value (₹) | Difference (₹) |
|---|---|---|---|
| MS plate @ ₹62/kg | 1,24,000 | 1,23,070 | 930 (short) |
| MS angle @ ₹64/kg | 96,000 | 92,160 | 3,840 (rejected) |
| Hex bolt @ ₹7.50 | 22,500 | 22,500 | 0 |
| Plain washer @ ₹1.20 | 6,000 | 5,880 | 120 (rejected) |
| Total, before GST | 2,48,500 | 2,43,610 | 4,890 |
Accounts pays ₹2,43,610 plus GST on that value. The ₹4,890 gap is settled with a debit note to the supplier.
The 60 kg of angle and 100 washers go back with a challan. The 2,000 bolts stay open on the PO for the next GRN. Our purchase return guide covers the return.
GRN and GST: why the receipt date matters
Under Section 16(2)(b) of the CGST Act, 2017, you can claim input tax credit only after you receive the goods. A dated, signed GRN is your proof of that receipt.
If goods on one invoice arrive in lots, credit is available only when the last lot arrives. So make one GRN per delivery, and date each one correctly.
GST law does not prescribe a GRN format; the GRN is an internal record. Still, add the supplier's invoice and e-way bill numbers. Our e-way bill format shows what that document holds.
Confirm the treatment for your business with your CA.
Three-way match: PO, GRN and invoice
Three-way matching means comparing the PO, the GRN and the invoice before you pay a supplier.
Check four things on each line: item, quantity, rate and supplier GSTIN. Pay only for the accepted quantity at the PO rate. Our purchase invoice format shows the invoice side.
The GRN sits in the middle. Without it, accounts can compare the order with the bill, but not with what reached the store.
Common GRN mistakes
- Writing the invoice quantity instead of the counted quantity.
- No rejected column, so rejected material quietly enters stock.
- A rejection with no reason, which leaves nothing to raise with the supplier.
- A GRN with no PO number, so nobody can check the rate.
- One GRN for two deliveries, which blurs the receipt dates.
- Filling the GRN days later, so the receipt date is wrong.
Where the GRN sits in TranZact
Most of these mistakes come from retyping. The PO sits in one file, the GRN in another, and the bill in Tally.
TranZact is manufacturing AI software used by 10,000+ manufacturers. In TranZact, the GRN is one step in a single purchase flow: MRP report → indent → RFQ → PO → GRN → payment.
The PO, the GRN and stock in sit on one system.
Entries sync one way to Tally, with no double entry.
Limits to know: TranZact does not replace your accounting software. Batch-wise stock and quality control sit on higher plans, as the table shows. Check Pricing for the plan that includes MRP and indent. Live in 2–3 weeks.
TranZact GRN and purchase facts (plans as listed on Pricing, 22 Oct 2026)
| Fact | Plan | Source |
|---|---|---|
| Purchase flow: MRP report → indent → RFQ → PO → GRN → payment | See Pricing for Planning (MRP + indent) | Purchase management, Pricing |
| Stock in, bin card, issue, multi-store, reorder, AI stock alerts | Stock tracking is on Grow and above; see Pricing for the rest | Inventory management, Pricing |
| Batch-wise stock tracking | Scale+ and Dominate | Pricing |
| Quality control (raw material and finished goods) | Dominate | Pricing |
| Store-level permissions | Dominate | Pricing |
| E-way bill and e-invoice (IRN) from the GST invoice | All plans | Confirmed by TranZact, 6 Oct 2026 |
| Tally and Zoho Books sync (one way); Busy integration | Grow and above | Pricing |