What is a job card?
A job card is the shop-floor record for one operation of a work order. It shows which item, how many, on which machine, by whom, and what actually came out. A good job card format has a header: job card no., work order no., item, operation, machine and planned qty. It also has a material issue table, a shift-wise time log, and OK, rejected and rework quantities with sign-offs.
This page covers the factory production job card. A job sheet is often just another name for it. MGNREGA job cards are government employment documents and are not covered here. Nor are workshop job cards, which list a vehicle, technician, labour and parts.
Job card vs work order vs job work
| Document | What it covers | Who fills it |
|---|---|---|
| Work order | The instruction to make an item in a set quantity, across all its operations | Planner or production head |
| Job card | One operation on one machine: material, time, output and rejection | Operator, QC and supervisor |
| Job work | Material sent to an outside party for processing, tracked with a delivery challan and ITC-04 | Stores, purchase and accounts |
One work order usually has several job cards. See our work order format and how to track job work and file ITC-04.
What each field in the job card format means
Header fields
- Job card no. and date issued: One running number per operation.
- Work order no. and customer / SO ref (optional): Links all job cards of one order.
- Item code, description and drawing / rev no.: As in your item master and BOM. A wrong revision scraps the lot.
- Operation no. and name, machine, planned qty and unit: For example, "20 – CNC turning" on CNC-03, from the routing.
- Operator, supervisor, planned start and finish, std time per piece (min): Efficiency is measured against the std time.
Material issue table
- Item code, description and unit: As listed in the bill of materials.
- Qty issued and qty consumed: What stores handed over, and what went into processing.
- Qty returned to store and scrap qty: Skip returns and you get a stock discrepancy.
Time and output log (one row per shift)
- Date, shift and operator: One row per shift.
- Start, end, break and run time (min): Run time is end minus start, minus break, minus downtime.
- Downtime (min) and downtime reason: Unplanned stops, with a real reason like tool change or power cut. Never just "misc".
- OK, rejected and rework qty: Good pieces, unusable pieces, and pieces that can be corrected. QC writes the last two.
- Remarks: Anything the next shift needs to know.
Summary and sign-off
Total processed, yield %, rejection %, run time and efficiency %, worked out as in the steps below. "Moved to" names the next operation or store; pieces waiting there are work in process. Operator, supervisor, QC and stores sign it off.
[[IMAGE {"type":"steps","title":"Work out the job card summary","items":["Processed = OK + rejected + rework","Yield % = OK ÷ processed","Rejection % = rejected ÷ processed","Earned minutes = OK × std time","Efficiency % = earned ÷ run minutes"]}]]
How to create and fill a job card, step by step
- The planner issues it: one card per operation, from the work order, BOM and routing.
- Stores writes the qty issued before work starts.
- The operator logs each shift the same day.
- QC records and signs the rejected and rework quantities.
- The supervisor closes it once issued = OK + rejected + rework + returned.
- Balance material goes back to store with a material transfer note.
Where TranZact fills it for you
Paper job cards work for one machine. Across many work orders, the header gets rewritten by hand and job cost comes weeks later.
TranZact is manufacturing AI software used by 10,000+ manufacturers. It runs work orders, process routing and production costing on one system, while your accounts stay in Tally. See the production management features.
Which TranZact feature holds each job card field
| Job card field | TranZact feature | Plan |
|---|---|---|
| Item, quantity, work order no. | Work orders | Grow and above |
| Materials to issue | Multi-level BOM and inventory issue | Grow and above |
| Operation sequence | Process routing | Grow and above |
| Job cost | Production costing | Grow and above |
| Machine | Machine planning | Dominate |
| Operation done outside | Sub-contracting | Grow and above |
This list does not cover the shift-wise time log, downtime reasons or sign-offs. Keep those in the Excel log.
TranZact production facts (as of 17 Nov 2026)
- Grow: ₹8,333/month billed yearly, 4 users. Includes routing, production costing and sub-contracting.
- Scale+: ₹16,666/month billed yearly, 8 users.
- Dominate: ₹30,000/month billed yearly, 12 users. Adds machine planning, quality control and custom document formats.
- Live in 2–3 weeks.
- Accounts stay in Tally, with one-way sync and no double entry.
Full plan details are on the pricing page.
Worked example: CNC turning of a steel flange
All numbers are illustrative. The Excel example uses the same numbers.
Table 1 (Example): job card header
| Field | Value |
|---|---|
| Job card / work order | JC-0412 / WO-0187 |
| Item | FL-080-EN8, steel flange 80 mm, Rev C |
| Planned qty | 480 Nos |
| Operation | 20 – CNC turning (face, OD, bore) |
| Machine | CNC-03 |
| Std time per piece | 2.5 min |
Table 2 (Example): material issued and consumed
| Field | Forged blank BL-080-EN8 |
|---|---|
| Unit | Nos |
| Qty issued | 490 |
| Qty consumed | 480 |
| Qty returned to store | 10 |
| Scrap qty | 9 (rejected pieces) |
Table 3 (Example): shift-wise time and output log
| Field | 10-Nov, Shift A | 10-Nov, Shift B | 11-Nov, Shift A |
|---|---|---|---|
| Operator | Operator 1 | Operator 2 | Operator 1 |
| Start – end | 07:00 – 15:00 | 15:00 – 23:00 | 07:00 – 15:00 |
| Break (min) | 30 | 30 | 30 |
| Downtime (min) | 40 | 25 | 65 |
| Downtime reason | Insert breakage, tool change | Power cut | Chuck jaw repair |
| Run time (min) | 410 | 425 | 385 |
| OK qty | 158 | 162 | 146 |
| Rejected qty | 3 | 4 | 2 |
| Rework qty | 2 | 1 | 2 |
Table 4 (Example): summary, yield and efficiency
| Measure | Working | Result |
|---|---|---|
| Total processed | 466 + 9 + 5 | 480 |
| Yield % | 466 ÷ 480 × 100 | 97.1% |
| Rejection % | 9 ÷ 480 × 100 | 1.9% |
| Run time | 410 + 425 + 385 | 1,220 min |
| Efficiency % | 466 × 2.5 ÷ 1,220 × 100 | 95.5% |
| Material check | 466 + 9 + 5 + 10 | 490 = qty issued |
The card balances, so the supervisor closes it. It is 14 OK pieces short of plan. The 65-minute chuck jaw repair is the first downtime to fix.
Common job card mistakes
- One card for the whole work order. You can't see which operation lost pieces.
- Filling the log at week's end. Counts from memory are guesses.
- Vague downtime reasons. "Misc" shows nothing to fix.
- Mixing rework with rejected. Rejection % looks worse than it is, and pieces that could be saved get scrapped.
- No entry for returned material. The system shows it consumed.
- Missing drawing revision. The lot gets made to an old drawing.
- Closing without the material check. Missing pieces go unnoticed.
- Using a job card for job work. That needs a delivery challan and ITC-04.
Job card PDF and Word questions
How to download a job card PDF?
Download the Excel file, then print it or save it as a PDF.
Is there a job card template in Word?
The format is in Excel because the log needs calculations. Copy it into Word to print.