Free Excel template

Production Plan Format: Free Excel Template + Example

A production plan format is a sheet that lists what your factory will make, how many, on which machine or line, and by when. A good format also checks two things before work starts: whether the machine has enough hours and whether the raw material is in stock. Download our free Excel format below: a blank sheet and a filled example for a small fabrication unit.

Download the Excel template

What is a production plan format?

A production plan format turns open orders into a work plan. It says what to make, how many, where and by when. It also checks machine hours and raw material first.

The owner uses it to promise dates. The planner or production head builds it. Stores issues material from it.

  • Daily plan: jobs on each machine, shift by shift.
  • Weekly plan: this week's orders, machines and dates. Our file uses this.
  • Monthly plan: rough capacity and raw-material buying.

Weekly is long enough to plan material and short enough to stay accurate. For the bigger picture, see our guide to the master production schedule.

Is there a free production planning template in Excel?

Yes. The download on this page has a blank weekly plan and the filled example below.

What each column in the production plan format means

A production schedule includes the order, item, quantity, machine hours, dates, material status and actual output.

ColumnWhat to enterFormula
SO no.Customer order this job is for—
ItemFinished product, named as in your BOM—
Due dateDate the customer expects dispatch—
Qty orderedQuantity on the sales order—
Finished stockReady stock of this item—
Qty to produceWhat you still need to makeQty ordered − Finished stock
Output/hrGood pieces this machine makes per hourFrom past records
Hours neededMachine time for this job, including changeoverQty to produce ÷ Output/hr + Changeover hours
Planned datesDates the job starts and endsFinish on or before the due date
Material statusOK, or what is short and when it arrivesFrom the material check
Good qtyGood pieces made, filled at day end—
RejectsPieces scrapped or sent for rework—

At the top, fill plan number, week, machine or line, prepared by and revision. Use one sheet per machine or cell. Raise the revision with every change, so everyone knows which copy is current.

How to fill the production plan, step by step

  1. List open orders. Write each pending order with item, quantity and due date.
  2. Subtract finished stock. Qty to produce = Qty ordered − Finished stock.
  3. Turn pieces into hours. Divide qty to produce by output per hour. Add the changeover time.
  4. Check capacity. Compare the machine's total hours with its free hours this week, after maintenance.
  5. Check material. Multiply each BOM quantity by qty to produce. Note any shortage against stock.
  6. Set priority and dates. Put the earliest due date first, unless material is short. Give each job a start and finish date.
  7. Fill actuals every day. At day end, enter good and rejected quantity. Short pieces carry over to next week's plan.

Step 5 needs a correct BOM. Start with our free bill of materials format, then read our guide to material requirement planning.

[[IMAGE {"type":"checklist","title":"Before you release the plan","items":["Finished stock subtracted","Hours include changeover, maintenance","Bottleneck load at most 100%","Every shortage has a date"]}]]

Worked example: one week in a small fabrication unit

A small fabrication unit plans week 48 (23–28 November 2026) for welding cell W1. W1 is the bottleneck, so the plan is built around it.

Table 1 (Example): weekly plan for welding cell W1

Example, illustrative numbers. Each job includes 1 hour of changeover.

Order and itemQty to produceHours neededDue date
SO-1041 Material-handling trolley120 − 20 = 100100 ÷ 5 + 1 = 2128 Nov
SO-1043 Storage rack frame80 − 0 = 8080 ÷ 4 + 1 = 2128 Nov
SO-1045 Machine guard panel70 − 10 = 6060 ÷ 6 + 1 = 112 Dec
Total24053—

Table 2 (Example): capacity check, load 106%

Example, illustrative numbers.

LineHours
Shift hours (6 days × 9 hours)54
Planned maintenance− 4
Available hours50
Load from Table 153
Capacity load (53 ÷ 50)106%

The plan is 3 hours over. SO-1045 is not due until 2 December, so it moves to Monday and Tuesday of next week.

New load: 42 ÷ 50 = 84%. The 8 spare hours cover a breakdown or a rush order.

Table 3 (Example): material check for SO-1041, castors short

Example, illustrative numbers.

MaterialNeeded for 100 trolleysIn stockShort
MS square tube 25×25 mm3.5 m × 100 = 350 m420 m0
Castor wheel 100 mm4 × 100 = 400260140
MS sheet base1 × 100 = 1001100
M8 bolt set16 × 100 = 1,6002,0000

Welding can start on Monday, because castors only go on at assembly. The planner asks purchase for 140 castors by Wednesday. Material status reads "Castors short 140, ordered".

Table 4 (Example): plan vs actual at week end

Example, illustrative numbers.

OrderPlanned qtyGood qtyRejected qty
SO-10411001002
SO-104380763
Total1801765

SO-1041 finished on time. SO-1043 is 4 pieces short, so those 4 become the first job of week 49.

Book a demo →

KPIs to track from your production plan

KPIs in production planning are a few numbers that show whether the plan held. Track these four, using the example week.

  • Plan adherence % = orders finished on time ÷ orders planned × 100. Example: 1 ÷ 2 = 50%.
  • Capacity load % = hours loaded ÷ hours available × 100. Example: 42 ÷ 50 = 84%.
  • Output vs plan = good qty ÷ planned qty × 100. Example: 176 ÷ 180 = 97.8%.
  • Rejection % = rejected qty ÷ (good qty + rejected qty) × 100. Example: 5 ÷ 181 = 2.8%.

If load sits near 100% week after week, read our guide to capacity requirements planning.

Common production plan mistakes

  • Not checking finished stock first. You make pieces already in the store.
  • Planning in pieces, never in hours. 100 trolleys still need 21 machine hours.
  • Ignoring maintenance and changeovers. No machine is free every shift hour.
  • No material check before the start date. The job stops for one missing part.
  • Loading the bottleneck above 100%. The plan is late before Monday.
  • No actual column. Next week repeats the same errors.
  • One file, no version. Three copies float on WhatsApp, and nobody knows which is right.

Where Excel stops and software takes over

This format works for one cell and a handful of orders. Past that, every number is typed by hand, and the sheet does not know today's stock.

The file sits with one person and goes stale when they are busy. That is a limit of the spreadsheet, not of your team.

TaskExcel formatTranZact
Finished and raw material stockTyped in from the store registerFrom stock in and issue entries
Material needed per orderBOM qty × order qty, by handMRP engine tells you what to buy and when
Machine hours and loadYour own formula per machineMachine planning (Dominate plan)
Accounts in TallyOrder and stock numbers typed againOne-way sync to Tally, no double entry

How TranZact fills the production plan for you

TranZact AI is manufacturing AI software used by 10,000+ manufacturers.

  • Production: multi-level BOM, work orders, process routing, sub-contracting and production costing, on one system.
  • Purchase: shortages move through MRP report → indent → RFQ → PO → GRN. Your purchase team raises each PO from the indent.
  • Stock: stock in, issue, multi-store, reorder and AI stock alerts, so system stock and physical stock match.
  • Accounts: accounting stays in Tally, with one-way sync and no double entry. Busy and Zoho Books sync too.

Plans start with Grow at ₹8,333 a month, billed yearly, for 4 users. Grow already includes planning (MRP + indent), multi-step BOM and production, and Tally, Busy and Zoho integration. There is no Free plan; only this Excel download is free. See pricing for every plan.

TranZact goes live in 2–3 weeks. Read more on production management and purchase management.

Don't be the bottleneck. Become the AI-Run Factory.

Bring one week of real orders and BOMs to a demo. We will run them through TranZact with you.

Born in India. Building for the world.

Book a demo →

Frequently asked questions

Should I make a daily, weekly or monthly production plan?

Most small factories plan weekly and adjust daily. Use a monthly view only for rough capacity and raw-material buying; the weekly sheet is where jobs get dates and machines.

How do I work out machine hours for an order?

Divide the quantity to produce by the output per hour for that item on that machine. Add changeover time, then compare the total with the machine's available hours for the week.

What if my plan is loaded above 100%?

Something has to move: shift a low-priority order to next week, add a shift or overtime, or send work out on job work. Never leave the plan above 100% and hope.

How does the production plan connect to the BOM?

The BOM gives quantity per unit for each component. Multiply it by the quantity to produce to get what the order needs, then check stock. Our free BOM format works with this sheet.

Can I keep planning in Excel and my accounts in Tally?

Yes, but every stock and order number gets typed twice. TranZact runs operations and syncs one way to Tally, so accounts stay in Tally with no double entry.

What is production planning and control, and is there a PDF?

Production planning and control means making the plan, then checking actual output against it. This sheet does both, with plan columns and actual columns. Print it or save it as a PDF from Excel.

Don’t be the bottleneck.
Become the AI-Run Factory.

Book a demo

Born in India. Building for the world.