A purchase order format is the standard layout a buyer uses to order goods from a supplier. It carries the PO number and date, buyer and supplier details with GSTIN, and each item's description, HSN code, quantity, unit, rate and GST. It also shows the total and the delivery and payment terms. Once the supplier accepts it, the PO is the agreed record of what will be supplied, at what price and by when.
What is a purchase order, and when should a factory raise one?
A purchase order (PO) is the buyer's written order to a supplier. Raise one once the need and the price are approved.
It sits in a chain: indent, quotation, PO, GRN, purchase invoice, payment. Once the supplier accepts it, the PO works as a contract.
A PO is not a GST document. You claim input tax credit on the supplier's invoice, but showing both GSTINs helps you check it. See purchase order vs proforma invoice.
What each column in the purchase order format means
Header
| Field | What to write | Why it matters |
|---|---|---|
| PO number and date | Next in your series | Quoted on the invoice |
| Buyer and supplier GSTIN | Names, addresses, GSTINs | State codes set the tax type |
| Ship-to | Receiving plant or store | Goods reach the right gate |
| Indent and quote reference | Both numbers and dates | Ties the PO to the price |
Item lines
| Field | What to write | Why it matters |
|---|---|---|
| Description and spec | Grade, size, drawing revision | Stops wrong material |
| HSN code | The item's HSN code | Sets the GST rate |
| Quantity and unit | One unit: kg, nos or metre | Avoids invoice disputes |
| Rate and taxable value | Rate before GST; qty × rate | Base for GST |
| GST | CGST + SGST, or IGST | Must match the invoice |
| Delivery date | Date needed per line | Lets you chase late lines |
Totals and terms
| Field | What to write | Why it matters |
|---|---|---|
| Totals | Figures and words | The amount you approved |
| Delivery and inspection | Part deliveries, freight, test certificate | Stores can reject off-spec material |
| Payment terms | E.g. 30 days from receipt | 45-day limit for micro and small suppliers |
The items usually come from your bill of materials format.
How to fill a purchase order, step by step
- Note the approved indent number.
- Add the supplier's quote number and date.
- Take the next PO number and today's date.
- Fill both parties' GSTINs and the ship-to plant or store.
- Add each line: spec, HSN, quantity, unit, rate, delivery date.
- Same GSTIN state code means CGST + SGST. Otherwise, IGST.
- Add totals in figures and words, then the terms.
- Sign within your approval limit and get written acceptance.
Where TranZact helps you raise the PO
An Excel PO works for a few orders a week. It gets hard when indents, POs, part deliveries and GRNs sit in separate files and WhatsApp chats.
In TranZact, the PO is one step in a single purchase management flow: MRP report, indent, RFQ, PO, GRN, payment. The MRP engine runs through your orders and BOMs, then tells you what to buy and when.
One honest limit: printing POs on your own layout needs custom document formats, which are on the Dominate plan only.
TranZact is used by 10,000+ manufacturers and goes live in 2–3 weeks.
TranZact purchase facts (as of 17 Nov 2026)
| Fact | Plan | Source page |
|---|---|---|
| Purchase flow: MRP report to payment | Grow and up | /solutions/factory-ai-os/purchase-management |
| Approvals and alerts; delivery and payment reminders | Grow and up | /pricing |
| Tally / Busy / Zoho integration | Grow and up | /pricing |
| Custom document formats | Dominate | /pricing |
| E-invoicing | All plans | /pricing |
Plans and prices are on the pricing page.
Worked example: a fabrication unit orders steel and fasteners
The numbers are illustrative. A Pune fabrication unit orders from a Pune trader. Both GSTINs start with 27, so CGST 9% and SGST 9% apply.
PO header
| Field | Example entry |
|---|---|
| PO number and date | PO/26-27/0142, 17-Nov-2026 |
| GSTINs (samples) | 27AAAAA0000A1Z5, 27BBBBB1111B1Z2 |
| Indent and quote | IND/26-27/0388; Q-1176, 14-Nov-2026 |
| Terms | Delivery 05-Dec-2026; mill test certificate; 30 days from receipt |
Item lines with CGST + SGST
| Item | Qty × rate (₹) | Taxable value (₹) | CGST 9% + SGST 9% (₹) |
|---|---|---|---|
| MS plate IS 2062, 10 mm (HSN 7208) | 2,000 kg × 62 | 1,24,000 | 11,160 + 11,160 |
| MS angle 50 × 50 × 6 mm (HSN 7216) | 1,500 kg × 64 | 96,000 | 8,640 + 8,640 |
| Hex bolt M12 × 50, grade 8.8 (HSN 7318) | 1,000 nos × 9.50 | 9,500 | 855 + 855 |
| Total | 2,29,500 | 20,655 + 20,655 |
Same order from an out-of-state supplier (IGST)
From a Gujarat supplier (GSTIN starting 24), the same order carries IGST 18% instead. The grand total stays the same.
[[IMAGE {"type":"compare","title":"Same order, two suppliers: CGST + SGST vs IGST","columns":["Pune supplier (27)","Gujarat supplier (24)"],"rows":[["Taxable value","₹2,29,500","₹2,29,500"],["Tax type","CGST 9% + SGST 9%","IGST 18%"],["GST amount","₹20,655 + ₹20,655","₹41,310"],["Grand total","₹2,70,810","₹2,70,810"]]}]]
PO vs quotation vs proforma vs GRN vs invoice
A quotation is the supplier's offer, and the PO accepts it. You claim GST credit on the supplier's tax invoice.
| Document | Who issues it | When | GST role |
|---|---|---|---|
| Quotation | Supplier | Before the order | None |
| Proforma invoice | Supplier | Before supply, often for an advance | Not a tax invoice |
| Purchase order | Buyer | After the price is agreed | Not a GST document |
| GRN | Buyer's stores | When goods arrive | Records receipt |
| Tax invoice | Supplier | When goods are supplied | Claim input tax credit on it |
Numbering, approvals and changes to a PO
Use one company-wide series: prefix, financial year, serial, e.g. PO/26-27/0142. Restart each April and never reuse a cancelled number.
Set approval limits in writing. For example, the owner signs any PO above a set value.
To change a sent PO, issue a dated revision such as PO/26-27/0142-R1. Get the supplier's written acceptance.
Common purchase order mistakes
- Units that don't match. PO in kg, invoice in nos.
- Rate with GST mixed in. Show GST in its own columns.
- Changes agreed on the phone. Issue a revised PO.
- Paying without a match. Check the PO against the goods received note format and purchase invoice format first.