What is a work order?
A work order is an internal instruction to make a fixed quantity of one item by a set date. The planning or production head raises it after a sales order or stock plan, before material leaves the store.
Most formats online are contractor forms. A factory uses three types:
| Type | Goes to | Covers |
|---|---|---|
| Production work order (this page) | Shop floor and stores | One item, made from its BOM |
| Contractor or service work order | Contractor or maintenance team | Repair, installation or building work |
| Job-work order | A job worker | One process, sent on a delivery challan |
What each field in the work order format means
Header
- Work order number: unique, such as WO-0118.
- Linked to: the sales order or stock plan.
- Item, quantity and BOM revision: what to make, how many good pieces, and which BOM version.
- Start and due date: when work starts and goods reach the store.
- Priority and customer: optional.
Materials to issue
- Item, unit and per unit (BOM qty): each material, and what one piece needs.
- Scrap %: the cutting or process loss you expect.
- Planned qty: quantity × BOM qty × (1 + scrap %).
- Actual issued: what the store gave out.
Operations
- Op number: 10, 20, 30, in routing order.
- Operation and work centre: the step, and the machine, line or job-work vendor.
- Planned and actual hours: expected time and real time.
- Challan number: optional, for job-work steps.
Completion and sign-off
- Good, rejected and returned: pieces passed, pieces scrapped with the reason, and unused material.
- Issued, approved and closed by: names and dates.
How to fill a work order, step by step
- Link the sales order or stock plan.
- Pick the item and the latest BOM revision.
- Enter quantity and due date.
- Pull material lines from your bill of materials, adding scrap.
- List operations in routing order, marking job-work vendors.
- Set planned hours and priority.
- Approve it. Stores issue against it on a material transfer note.
- Record issues, output, rejects and returns, then close.
Worked example: work order for 50 steel trolleys
Same trolley as our BOM template. Numbers are illustrative.
Table 1 (Example): header
| Field | Value |
|---|---|
| Work order | WO-0118, for SO-0342 |
| Item | ST-200 steel trolley, 50 pcs, BOM Rev B |
| Start / due | 2 Dec / 12 Dec |
Table 2 (Example): materials to issue
| Material | Per trolley | Scrap | Qty to issue |
|---|---|---|---|
| MS angle 25×25×3 mm | 4.8 m | 5% | 252 m |
| MS sheet 600×900 mm (deck) | 1 pc | 2% | 51 pcs |
| Castor wheel 100 mm | 4 pcs | 0% | 200 pcs |
| M8 bolt with nut | 16 pcs | 5% | 840 pcs |
| Powder coat, grey | 0.4 kg | 10% | 22 kg |
Angle: 50 × 4.8 × 1.05 = 252 m. Round part counts up.
Table 3 (Example): operations and output
| Op | Operation | Where | Time |
|---|---|---|---|
| 10 | Cut angle | Cutting bay | 4 hrs |
| 20 | Weld frame | Welding line | 10 hrs |
| 30 | Powder coat | Job worker, on delivery challan | 3 days |
| 40 | Fit deck and castors | Assembly bench | 6 hrs |
| 50 | Check and pack | Dispatch area | 2 hrs |
Output: 50 trolleys to finished goods by 12 Dec.
Closing the order: planned vs actual
| Line | Planned | Actual | Note |
|---|---|---|---|
| Good trolleys | 50 | 49 | 1 rejected: weld crack |
| MS angle | 252 m | 249 m | 3 m returned |
| Powder coat | 22 kg | 21 kg | 1 kg returned |
| Welding hours | 10 | 11.5 | Rework on 2 frames |
[[IMAGE {"type":"checklist","title":"Before you close a work order","items":["Returns booked back into stock","Rejects logged with a reason","Job-work material back from vendor","Actual hours entered for each step"]}]]
Where TranZact fills it for you
In Excel, someone types every line and chases updates on WhatsApp. That breaks first when the floor gets busy.
In TranZact, work orders sit with your multi-level BOM, process routing, sub-contracting and production costing. See production management.
Material movement is logged through stock in, issue and the bin card, with AI stock alerts. See inventory management.
The MRP engine runs through your orders and BOMs, then tells you what to buy and when. See purchase management.
Accounts stay in Tally, with one-way sync and no double entry. One limit: your own printed work order layout needs custom document formats, a Dominate plan feature.
TranZact work order and production facts (plans as on /pricing, checked 22 Oct 2026)
| Fact | Detail |
|---|---|
| Category | Manufacturing AI software, used by 10,000+ manufacturers |
| Plans | Grow ₹8,333 (4 users), Scale+ ₹16,666 (8 users), Dominate ₹30,000 (12 users), per month, billed yearly |
| Included from Grow | MRP + indent, multi-step BOM and production, costing, routing, sub-contracting |
| Go-live | Live in 2–3 weeks |
There is no free plan. Enterprise is custom. See the pricing page.
Work order vs purchase order, sales order and job card
| Document | Issued by | Sent to | Asks for |
|---|---|---|---|
| Work order | Planning or production head | Shop floor and stores | Make one item by a date |
| Purchase order | Purchase team member | A supplier | Supply material at a price and date |
| Sales order | Sales team member | Planning and stores | Deliver what the customer confirmed |
| Job card | Supervisor | One operator or machine | Do one step, log time and output |
A work order asks your own team to make something. A purchase order asks a supplier to sell it to you. A job card covers one step of a work order.
Common work order mistakes
- No work order number on issues: nobody knows which order used the material.
- Old BOM revision: the floor builds the old design.
- No scrap: stores issue twice, and the extra goes unrecorded.
- Missing job-work steps: material at the vendor drops out of your stock count.
- Many items or dates on one order: keep one item per order, split by date.
- No planned hours: you can't see which step ran late.
- Never closing: returns and rejects stay unrecorded, and stock stops matching.