Exceptions started surfacing early, reducing daily firefighting and urgent purchases. especially during peak weeks.

15%

Reduction in rework/rejection loops

15%

Reduction in rework/rejection loops

16%

Improvement in on-time dispatch

16%

Improvement in on-time dispatch

2 days

Faster internal approvals cycle

2 days

Faster internal approvals cycle

Hero Background

About Aplos Ventures Private Limited

About Aplos Ventures Private Limited

Aplos Ventures Private Limited operates from Mumbai and builds sub-assemblies for OEM customers. As a small-scale engineering unit running single shift, they work with a make-to-stock model and single stores. They needed a centralised workflow to reduce daily follow-ups and keep commitments predictable.

Workspace Icon

Engineering

Industry

Workspace Icon

Engineering

Industry

Workspace Icon

Small

Company Size

Workspace Icon

Small

Company Size

Workspace Icon

Mumbai

Location

Workspace Icon

Mumbai

Location

Workspace Icon

Enquiry-to-order control for custom jobs and drawing revisions

Use Cases

Workspace Icon

Enquiry-to-order control for custom jobs and drawing revisions

Use Cases

Challenges

Inspection status was confirmed via whiteboard planning, so WIP clarity broke during extended shifts during peak weeks.

Raw Bars shortages showed up late, causing emergency buys and delays on sub-assemblies.

Dispatch dates were committed before checks for promise-date accuracy, causing reshuffles (bulk dispatch at month-end).

Daily planning with one live view

Daily planning with one live view

Daily planning with one live view

Earlier, Aplos Ventures Private Limited relied on planner’s notebook and calls to confirm fitment progress. When priorities changed, different teams carried different versions of the plan. A centralised workflow captured stage updates at source, so WIP moved with clear ownership. The daily review shifted from collecting updates to resolving exceptions. Supervisors started closing handovers on time, improving predictability during single shift.

Earlier, Aplos Ventures Private Limited relied on planner’s notebook and calls to confirm fitment progress. When priorities changed, different teams carried different versions of the plan. A centralised workflow captured stage updates at source, so WIP moved with clear ownership. The daily review shifted from collecting updates to resolving exceptions. Supervisors started closing handovers on time, improving predictability during single shift.

Shortage list with vendor dates

Shortage list with vendor dates

Shortage list with vendor dates

Earlier, buying for raw bars was triggered after shortages hit the shopfloor. Follow-ups lived in personal reminders, so receipts slipped during busy days. Requirements were linked to live orders and tooling components, creating a daily shortage list. Vendors were followed up against dates, not memory, and approvals became faster. The team reduced emergency purchases and avoided excess on slow movers across job-site plus main warehouse. during vendor delays.

Earlier, buying for raw bars was triggered after shortages hit the shopfloor. Follow-ups lived in personal reminders, so receipts slipped during busy days. Requirements were linked to live orders and tooling components, creating a daily shortage list. Vendors were followed up against dates, not memory, and approvals became faster. The team reduced emergency purchases and avoided excess on slow movers across job-site plus main warehouse. during vendor delays.

Dispatch readiness checks

Dispatch readiness checks

Dispatch readiness checks

Earlier, dispatch dates were committed before checks on outside processing. Packing, QA clearance, and paperwork were tracked in different places. Readiness gates were added so jobs were released only when documents were complete. Customers got clearer dates, and escalations reduced because holds had visible reasons. Dispatch planning became steadier even with a mix of make-to-stock and make-to-order model and distributors.

Earlier, dispatch dates were committed before checks on outside processing. Packing, QA clearance, and paperwork were tracked in different places. Readiness gates were added so jobs were released only when documents were complete. Customers got clearer dates, and escalations reduced because holds had visible reasons. Dispatch planning became steadier even with a mix of make-to-stock and make-to-order model and distributors.

More like this

Numakers Asia LLP

Numakers Asia LLP, a small packaging manufacturer in Surat, faced significant operational challenges, including miscommunication on vendor commitments and a lack of synchronization between dispatch processes. To address these issues, they implemented a centralized workflow that streamlined coordination across departments. This transformation led to improved execution predictability and reduced reliance on individual team members for updates. Discover how this approach not only stabilized their planning but also enhanced their overall operational efficiency.

Read More

Hira packaging solutions

Hira Packaging Solutions implemented a centralized workflow to tackle significant operational challenges, such as unclear work-in-progress quantities and disjointed communication across departments. This approach transformed their order-to-dispatch processes, leading to improved execution predictability and streamlined reporting. The team transitioned from reliance on scattered tools and outdated methods to a cohesive system, enhancing accountability and reducing the frequency of escalations. Discover how these strategic changes reshaped their daily operations and outcomes.

Read More

Omkar Industries

In a bid to enhance operational efficiency, Omkar Industries adopted a centralized workflow solution to tackle persistent coordination challenges. The company faced issues with inconsistent inventory tracking, conflicting reports from different systems, and difficulty in managing vendor follow-ups. By streamlining these processes, they aimed for smoother inter-departmental handovers and improved execution predictability, setting the stage for a more cohesive work environment.

Read More

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders