Connecting materials to live orders at Aries Alloys

Connecting materials to live orders at Aries Alloys

Connecting materials to live orders at Aries Alloys

Daily reviews got shorter because teams worked off the same status and dates. (case 418)

20%

Reduction in rework/rejection loops

20%

Reduction in rework/rejection loops

15%

Improvement in on-time dispatch

15%

Improvement in on-time dispatch

₹8 L/yr

Working capital freed from slow-movers

₹8 L/yr

Working capital freed from slow-movers

Hero Background

About Aries Alloys

About Aries Alloys

Aries Alloys operates from Mumbai and builds brackets for repeat B2B buyers. As a micro-scale fabrication unit running single shift, they work with a make-to-stock model and job-site plus main warehouse. They needed a centralised workflow to reduce daily follow-ups and keep commitments predictable.

Workspace Icon

Fabrication

Industry

Workspace Icon

Fabrication

Industry

Workspace Icon

Micro

Company Size

Workspace Icon

Micro

Company Size

Workspace Icon

Mumbai

Location

Workspace Icon

Mumbai

Location

Workspace Icon

Dispatch readiness with QA and packing checks for fabricated jobs

Use Cases

Workspace Icon

Dispatch readiness with QA and packing checks for fabricated jobs

Use Cases

Challenges

Machining status was updated via WhatsApp-based follow-ups, so WIP clarity broke during extended shifts during peak weeks.

Fasteners shortages showed up late, causing emergency buys and delays on machine frames. when multiple orders overlapped.

Dispatch dates were dispatched before checks for outside job-work, causing reshuffles (inventory closing pressure).

Daily planning with one live view

Daily planning with one live view

Daily planning with one live view

Earlier, Aries Alloys relied on WhatsApp-based follow-ups and calls to confirm painting progress. When priorities changed, different teams carried different versions of the plan. A centralised workflow captured stage updates at source, so WIP moved with clear ownership. The daily review shifted from collecting updates to resolving exceptions. Supervisors started closing handovers on time, improving predictability during staggered shifts.

Earlier, Aries Alloys relied on WhatsApp-based follow-ups and calls to confirm painting progress. When priorities changed, different teams carried different versions of the plan. A centralised workflow captured stage updates at source, so WIP moved with clear ownership. The daily review shifted from collecting updates to resolving exceptions. Supervisors started closing handovers on time, improving predictability during staggered shifts.

Materials linked to live orders

Materials linked to live orders

Materials linked to live orders

Earlier, buying for fasteners was triggered after shortages hit the shopfloor. Follow-ups lived in personal reminders, so receipts slipped during busy days. Requirements were linked to live orders and structures, creating a daily shortage list. Vendors were followed up against dates, not memory, and approvals became faster. The team reduced emergency purchases and avoided excess on slow movers across two warehouses. around month-end dispatches.

Earlier, buying for fasteners was triggered after shortages hit the shopfloor. Follow-ups lived in personal reminders, so receipts slipped during busy days. Requirements were linked to live orders and structures, creating a daily shortage list. Vendors were followed up against dates, not memory, and approvals became faster. The team reduced emergency purchases and avoided excess on slow movers across two warehouses. around month-end dispatches.

Fewer last-minute dispatch changes

Fewer last-minute dispatch changes

Fewer last-minute dispatch changes

Earlier, dispatch dates were committed before checks on fitment issues. Packing, QA clearance, and paperwork were tracked in different places. Readiness gates were added so jobs were released only when documents were complete. Customers got clearer dates, and escalations reduced because holds had visible reasons. Dispatch planning became steadier even with a make-to-order model and project-based customers.

Earlier, dispatch dates were committed before checks on fitment issues. Packing, QA clearance, and paperwork were tracked in different places. Readiness gates were added so jobs were released only when documents were complete. Customers got clearer dates, and escalations reduced because holds had visible reasons. Dispatch planning became steadier even with a make-to-order model and project-based customers.

More like this

Numakers Asia LLP

Numakers Asia LLP, a small packaging manufacturer in Surat, faced significant operational challenges, including miscommunication on vendor commitments and a lack of synchronization between dispatch processes. To address these issues, they implemented a centralized workflow that streamlined coordination across departments. This transformation led to improved execution predictability and reduced reliance on individual team members for updates. Discover how this approach not only stabilized their planning but also enhanced their overall operational efficiency.

Read More

Hira packaging solutions

Hira Packaging Solutions implemented a centralized workflow to tackle significant operational challenges, such as unclear work-in-progress quantities and disjointed communication across departments. This approach transformed their order-to-dispatch processes, leading to improved execution predictability and streamlined reporting. The team transitioned from reliance on scattered tools and outdated methods to a cohesive system, enhancing accountability and reducing the frequency of escalations. Discover how these strategic changes reshaped their daily operations and outcomes.

Read More

Omkar Industries

In a bid to enhance operational efficiency, Omkar Industries adopted a centralized workflow solution to tackle persistent coordination challenges. The company faced issues with inconsistent inventory tracking, conflicting reports from different systems, and difficulty in managing vendor follow-ups. By streamlining these processes, they aimed for smoother inter-departmental handovers and improved execution predictability, setting the stage for a more cohesive work environment.

Read More

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders