Sales and Operations Planning (S&OP): Steps for Factories

6 min read

By

TranZact Solutions Team

· Published

Hero Background
Functions of ERP System Explained

What is sales and operations planning?

Sales and operations planning (S&OP) is a monthly process where sales, production, purchase and finance agree on one plan. The plan says how much you expect to sell, how much you can make, and what you must buy to make it. It runs in five steps: gather data, plan demand, plan supply, balance the two, and sign off. In a small factory, it can be a one-hour monthly meeting between the owner, the sales head and the production head.

Say sales expects a big jump in orders next month. Can the shop floor make them? Can purchase get the steel in time? S&OP answers both questions before the promise reaches the customer.

The term dates to the 1980s and is credited to Richard Ling of Oliver Wight.

What is the main goal of S&OP?

The main goal is one agreed plan that balances demand with capacity, stock and cash. Sales, production and purchase work from the same numbers, not three versions of them.

When it works, you see fewer stockouts, less excess stock and more orders dispatched on time. It is a tactical plan. It works at product-family level, not item by item.

The S&OP process in 5 steps

Most guides describe five steps. ASCM lists six, with finalisation and implementation as its own step. Lists of seven steps cover the same cycle, split finer with event planning and a review.

1. Gather data

Pull sales history, open sales orders, current stock, open purchase orders and rough monthly capacity. Take every number as of one date. Then the meeting argues about the plan, not the data.

2. Plan demand

Sales turns history and open orders into a forecast by product family for the next few months. Add known events, like a new customer or a festive peak. Our guide to demand management covers this step in depth.

3. Plan supply

Production checks machines, shifts and people against the forecast. Purchase checks raw material stock and vendor lead times. Note every place where demand runs past what you can make or buy.

4. Balance supply and demand

Before the meeting, the planning lead drafts options for each gap. The usual options are overtime, sub-contracting, moving an order date or buying material ahead.

5. Sign off and execute

The owner picks one option per gap and signs off the plan. That plan then feeds the month's production schedule and purchase plan.

What happens in an S&OP meeting?

In an owner-led manufacturer, the S&OP meeting is short and decision-led. The owner chairs it. The sales, production, purchase and accounts heads attend.

It is not a status update. It must end with written decisions: what to make, what to buy ahead, which orders move, and who acts by when.

A 60-minute S&OP meeting agenda
  1. Review last month: plan vs actual

  2. Agree demand by product family

  3. Check capacity and material gaps

  4. Pick one fix per gap

  5. Confirm names and dates

Why S&OP fails in small factories

Most failures come from the tools, not the people. Tally, Excel and WhatsApp were never built to hold one shared plan.

  • Data is scattered. Orders sit in Excel, stock in Tally, vendor updates on WhatsApp. Fix: keep orders, stock and purchase in one place.

  • Stock figures are out of date. Entries get skipped when the shop floor is busy. Fix: record each movement when it happens.

  • The plan never reaches purchase. Decisions stay in the meeting notes. Fix: run material planning from the signed plan the same day.

  • The meeting gets skipped. Busy months push it out first. Fix: fix a monthly date and keep it to one hour.

From signed S&OP plan to material at the gate
  1. Signed S&OP plan by family

  2. Production schedule by item

  3. MRP report: what to buy

  4. Indent and RFQ to vendors

  5. Purchase order, then GRN

How TranZact helps a manufacturer run S&OP

TranZact is manufacturing AI software used by 10,000+ manufacturers. Sales orders, stock, BOMs and production sit in one place. So step 1 becomes a report, not a week of copying into Excel.

  • Sales: enquiry, quotation, order timeline and dispatch, plus sales and purchase planning.

  • Production: multi-level BOM, work orders, process routing, sub-contracting and production costing.

  • Purchase: the MRP engine runs through your orders and BOMs, then tells you what to buy and when.

  • Purchase flow: MRP report → indent → RFQ → PO → GRN, so the signed plan reaches vendors.

  • Stock: a photo of a paper entry becomes a system entry. Reorder levels and AI stock alerts flag shortages.

  • The meeting: AI tasks and dashboards, 65+ reports, and approvals and alerts.

  • Accounts: stay in Tally, Busy or Zoho Books, with one-way sync and no double entry.

Machine planning and real-time MIS are on the Dominate plan; see pricing for what each plan includes. TranZact goes live in 2–3 weeks.

One honest limit: TranZact gives you current numbers, but it does not make the trade-offs. The owner and the heads still decide who gets overtime and which order moves.

Book a demo →

Example: a monthly S&OP for an engineering-goods factory

Here is a one-page S&OP sheet for an engineering-goods plant. The numbers are illustrative, made up to show the method.

Product family

Demand next month

What we can make

Gap and decision

Flanges

9,000 pcs

8,000 pcs

1,000 short: sub-contract machining

Shafts

3,000 pcs

4,000 pcs

Spare capacity: pull a later order forward

Brackets

5,000 pcs

5,000 pcs

Steel covers 3,500 only: buy ahead now

The brackets row is the one most teams miss. Capacity looks fine, but material runs out first. Each gap ends in one decision with a name against it.

S&OP vs SIOP vs IBP vs MPS

These terms sit at different levels of the same planning chain. Many companies use S&OP and SIOP to mean the same thing.

Term

What it does

Level

S&OP

Balances demand and supply

Product families, up to 18 months

SIOP

Adds inventory investment to that balance

Same as S&OP

IBP

Broader plan, more weight on finance

Longer term than S&OP

MPS

Turns the plan into what to make, and when

Individual items

MRP

Works out what material to buy, and when

Raw materials and parts

Read more on the master production schedule, material requirement planning and aggregate planning vs MPS.

Why sales and operations clash, and how S&OP fixes it

Sales decides what the customer gets and by when. Operations decides what the plant can actually deliver. Each sees half the picture.

So sales promises a date, and production finds out later that machines or material can't meet it. S&OP gives both one number for the month. Sales quotes dates from that number, checked against capacity requirements.

How to run your first S&OP this month

  1. Book a one-hour slot on a fixed date each month.

  2. Pick three to five product families, not every item.

  3. Pull sales history, open orders, stock, open POs and capacity as of one date.

  4. Ask sales for a forecast by family for the next three months.

  5. List every gap with one proposed fix before the meeting.

  6. Write down decisions, names and dates, and send them to purchase that day.

Make the next promise one you can keep

Pick a date for your first S&OP meeting this month. If gathering the numbers is the hard part, let us show you how TranZact keeps them in one place.

Don't be the bottleneck. Become the AI-Run Factory.

Book a demo →

Check out other blogs

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders