Daily Production Report Format (Free Excel + Example)

A one-page shift report for planned vs actual output, rejection, downtime and material. Download the blank Excel format and a filled example from a plastic moulding unit, with every column explained.

Download the Excel template

A daily production report (DPR) is a one-page record of what each machine or line made in a shift. It shows planned quantity, actual quantity, good and rejected pieces, downtime with reasons, and material used. The supervisor fills it at the end of each shift, and the production head checks it the next morning against the plan. Our free Excel format has these columns with the formulas built in, plus a filled example from a plastic moulding unit.

What is a daily production report?

In a factory, DPR means daily production report, not the film-shoot report that also shows up in search. It records what was made, what was lost and why. The owner usually sees a weekly roll-up.

What each column in the DPR format means

The sheet has 6 header fields filled once per shift, then 12 columns filled once per machine.

FieldWhat to writeFormula / rule
DateDate of the shiftOne sheet per shift
ShiftShift name and timinge.g. A, 06:00–14:00
Plant / unitPlant, shop or baySame name every day
Shift length (min)Total minutes in the shift8 hours = 480
Planned break (min)Lunch and tea breaksPlanned run time = shift length − break
Filled by / checked bySupervisor and production headBoth sign
1. Machine / work orderMachine ID and its work orderFrom the day's plan
2. ItemItem code and short nameSame code as stores and the BOM; add the unit if not pieces
3. Planned qtyQuantity planned for this shiftFrom the work order
4. Produced qtyEverything that came off the machineActual count, not the target
5. Rejected qtyPieces scrappedCannot be reworked
6. Rework qtyPieces held for reworkNot good until they pass
7. Good qtyPieces fit to move aheadProduced − Rejected − Rework
8. Rejection %Share of output scrappedRejected ÷ Produced × 100
9. Achievement %Share of plan met with good piecesGood ÷ Planned × 100
10. Downtime (min)Minutes stopped in planned run timeSum of all stops
11. Downtime reasonReason code plus one short noteFrom the code list, e.g. BD: heater band failed
12. Material issued / returned (kg)Received from stores, then sent back unusedConsumed = issued − returned

The starter reason codes are BD (breakdown), MC (mould or die change), MW (material wait), PC (power cut), QH (quality hold) and NO (no operator). Edit them to suit your plant, but keep the list fixed once set.

Utilisation is worked out in the shift summary, not on each machine row. Run time = planned run time − downtime. Utilisation % = run time ÷ planned run time × 100.

How to fill the DPR, step by step

  1. Before the shift: copy planned qty for each machine from the day's work orders.
  2. During the shift: log each stop as it happens, with minutes and a reason code.
  3. At shift end: count produced pieces, then separate rejected and rework pieces.
  4. Material: write raw material issued, then weigh and return what is left to stores.
  5. Formulas: the sheet works out good qty, rejection % and achievement %. The shift summary works out utilisation %.
  6. Sign off: the supervisor signs, and the production head checks it next morning against the plan.

Update the DPR every shift, not once a day. Minutes of downtime are forgotten by evening. Material issued should follow the quantities in your bill of materials format.

[[IMAGE {"type":"compare","title":"Shift data: Excel sheet vs TranZact","columns":["Excel DPR","TranZact"],"rows":[["Work order","Copied by hand","Work orders in one system"],["Stock","Retyped for stores","Stock in, issue, multi-store"],["Costing","Worked out in another sheet","Production costing"],["Reports","Built by hand","65+ reports and dashboards"]]}]]

Book a demo →

Worked example: a plastic moulding unit, one shift, three machines

All numbers below are illustrative. Shift A runs 06:00–14:00, which is 480 minutes. With a 30-minute break, each machine has 450 minutes of planned run time.

Table 1 (Example): DPR for Shift A

FieldIMM-01IMM-02IMM-03
Work order / itemWO-1121, 1 L containerWO-1122, 1 L lidWO-1123, 28 mm cap
Planned qty (pcs)1,5002,4006,000
Produced qty1,4001,9505,800
Rejected / rework28 / 015 / 1558 / 0
Good qty1,3721,9205,742
Rejection %2.0%0.8%1.0%
Achievement %91.5%80.0%95.7%
Downtime (min) / reason30 / MC90 / BD15 / MW
Material issued / returned (kg)175 / 3075 / 2445 / 20

Check one row yourself. IMM-02 produced 1,950 lids, with 15 rejected and 15 on rework. Good qty is 1,950 − 15 − 15 = 1,920, and 1,920 ÷ 2,400 = 80.0%.

Table 2 (Example): shift summary

MeasureShift A totalHow it is worked out
Planned run time1,350 min3 machines × 450
Downtime135 minBD 90 + MC 30 + MW 15
Run time1,215 min1,350 − 135
Utilisation90.0%1,215 ÷ 1,350 × 100
Material issued295 kg175 + 75 + 45
Material returned74 kg30 + 24 + 20
Material consumed221 kg295 − 74

What the production head reads from this report

IMM-02 lost 90 minutes to a heater band failure and reached 80.0% of plan. The gap of 480 lids goes into tomorrow's plan.

IMM-01's 2.0% rejection points at the mould change. And 74 kg of unused material goes back to stores, or stock will be wrong.

Shift-wise, machine-wise or plan-vs-actual: which DPR layout fits?

LayoutOne row isFits
Machine-wise (this template)One machine, one shiftMoulding, machine shops, press shops
Line-wiseOne line, one shiftAssembly or packing lines making one product
Plan-vs-actual roll-upOne work order or item, one weekThe owner's weekly review

If one item passes through several machines, the process routing decides which machine reports which step.

A production schedule is made before the shift and says what to make, on which machine, and when. The report is filled after the shift and records what actually happened. Compare the two every day.

Common DPR mistakes

  • Adding pieces of different items into one total. Fix: track achievement % per item, or convert output to value in ₹.
  • Counting rework as good on the same day. Fix: keep rework in its own column until it passes.
  • Blank or "misc" downtime reasons. Fix: use the fixed reason codes, with minutes against each.
  • Mixing units for the same item. Fix: use the one unit stores uses for that item.
  • Filling the sheet next day from memory, or writing targets instead of counts. Fix: fill it before the shift ends, from actual counts.
  • The DPR never reaching stores. Fix: send material returns and output to stores the same day.

Many shop floors still write the DPR in a paper register first. TranZact's AI reads a photo of a paper entry and turns it into a system entry, with no typing.

Where the DPR breaks in Excel, and where TranZact fills it for you

Excel works for one shift on a few machines. It breaks when the same numbers have to be typed again into stock, purchase and costing. Each retyping is a chance for the sheet and the stores count to drift apart.

TranZact is manufacturing AI software used by 10,000+ manufacturers. The work order, routing, stock and costing sit in one system. Its reports and dashboards replace the sheet built by hand.

TranZact production facts (as of 18 Nov 2026)

  • Production: multi-level BOM, work orders, process routing, sub-contracting and production costing. See production management.
  • Inventory: stock in, issue, multi-store, reorder and AI stock alerts.
  • Reports: 65+ reports, plus AI tasks and dashboards.
  • Dominate plan only: real-time MIS, machine planning, and quality control for raw material and finished goods.
  • Accounts: stay in Tally, Busy or Zoho Books. One-way sync, no double entry.
  • Plans: billed yearly, from Grow at ₹8,333/month for 4 users. There is no free plan. See pricing.
  • Go-live: live in 2–3 weeks.

TranZact does not have a screen called "Daily Production Report". In a demo, bring your current DPR and see how your work orders, stock and reports would look.

Start with the free Excel format today. Don't be the bottleneck. Become the AI-Run Factory.

Book a demo →

Frequently asked questions

Is the daily production report format free to download?

Yes. The Excel file is free with no sign-up. It has a blank format, a filled example and a starter list of downtime reason codes you can edit.

Should I make one DPR per machine or one per line?

Use one row per machine per shift if machines run different items, as in moulding or a machine shop. Use one row per line if the line makes one product, as in assembly.

Who should fill the DPR and who should check it?

The shift supervisor fills it before leaving, from actual counts and the downtime log. The production head checks it the next morning against the plan.

Why does my production report never match my stock?

Usually the material issued, returned and produced on the DPR never reaches stock, or rework is counted as good too early. Return unused material to stores the same day, and count rework only once it passes.

When should a factory move the DPR from Excel to software?

When the same numbers have to be typed again into stock, purchase and costing. Or when more than one shift or plant reports.

Does TranZact replace the daily production report sheet?

TranZact keeps work orders, process routing, stock and production costing in one system, with 65+ reports and dashboards. Real-time MIS is on the Dominate plan, and accounts stay in Tally.