Machine Planning: How to Plan Machine Capacity (India)

6 min read

By

TranZact Solutions Team

· Published

Hero Background
Functions of ERP System Explained

What is machine planning?

Machine planning is deciding which job runs on which machine, in what order and when, so orders finish on time without overloading any machine. Work out each machine's real available hours: machines × hours per shift × shifts × working days, minus setup, maintenance and breakdowns. Then add up the hours your open orders need from it. Wherever the load is higher than the hours, move, split or outsource jobs.

Not the same as a "planning machine". A planing or planer machine is a metal-cutting machine tool that makes flat surfaces. This page is about planning work on your machines.

How to calculate machine capacity

Capacity = machines × hours per shift × shifts per day × working days × planned uptime factor. The uptime factor takes out scheduled maintenance, breaks, power cuts and breakdowns. It covers setup only if setup isn't already in load. This guide puts setup in load.

Design vs effective capacity

Design capacity is every hour the machine could run. Effective capacity is design capacity minus planned allowances like maintenance, breaks and any setup not counted in load. Always plan against effective capacity, never the 24×7 figure.

Machine load and load ratio

Load is the setup hours plus run hours of every open job on a machine. Load ratio = load ÷ effective capacity. Above 1.0 means the machine is overloaded and some jobs will be late.

Worked example: 3 CNC machines, 2 shifts, 6-day week

Take 3 CNC machines running two 8-hour shifts, six days a week, with Sunday off. That gives 26 working days in the month. The numbers below are illustrative.

  • Design capacity per machine: 8 × 2 × 26 = 416 hours.

  • Effective capacity at an 85% uptime factor: 416 × 0.85 ≈ 354 hours. Setup is already in the load hours.

  • Across 3 machines: about 1,061 effective hours.

Now add up the setup and run hours each machine needs for open orders:

Machine

Effective hours

Load hours

Load ratio

CNC-1

354

390

1.10 (overloaded)

CNC-2

354

300

0.85

CNC-3

354

330

0.93

The total load is 1,020 hours, so the month fits overall. But CNC-1 is 36 hours short. If CNC-2 can run the same operation, move about 40 hours of work there, and both stay under 1.0.

The worked example at a glance
  • 1,248 design hours a month, 3 CNCs

  • 1,061 effective hours at 85% uptime

  • 0.96 overall load ratio: the month fits

  • 1.10 CNC-1 load ratio: overloaded

How to do machine planning in 6 steps

  1. List machines and real shift hours. Note shifts, weekly offs and planned maintenance for each machine.

  2. Take open orders and their routing. Routing shows which operation runs on which machine. See routing in manufacturing.

  3. Add setup and run time per job. Run time is quantity × cycle time per piece. Add setup once per batch.

  4. Compare load to effective capacity. Work out the load ratio for each machine, week by week.

  5. Sequence the jobs. Go by due date first. Group jobs with similar setups. Keep the bottleneck machine busy at all times.

  6. Check material, release and review. Release a work order only when its material is ready. Compare actual output with the plan every day.

Excel or software: when to move machine planning into a system

Excel works for a few machines and steady orders. These are the signs it has run out:

  • Orders and due dates change every day, and the sheet can't keep up.

  • Many jobs share the same machines, so clashes show up only on the shop floor.

  • One person owns the sheet, and the plan stalls when they are away.

  • The plan no longer matches what the machines actually ran.

When you see these signs, check five points in any software.

What to check in machine planning software
  • Plan built from your work orders

  • Same BOM and routing as production

  • Material check before releasing a job

  • Production costing on every job

  • Tally sync with no double entry

For a wider list of checks, see our production management software buying guide.

How TranZact handles machine planning

TranZact is manufacturing AI software used by 10,000+ manufacturers. Machine Plan is part of the production module. It sits next to Multi-Level BOM, Work Order, Process Routing, Sub Contracting and Production Costing.

Material comes before release. The MRP engine runs through your orders and BOMs, then tells you what to buy and when. Purchase then runs from MRP report to indent, RFQ, PO and GRN.

Accounting stays in Tally, Busy or Zoho Books. Operations run in TranZact, with one-way sync and no double entry. TranZact goes live in 2–3 weeks, without consultants or an IT team.

One limit to know: machine planning is on the Dominate plan (₹30,000/month billed yearly, 12 users). It is not in Grow or Scale+. See pricing for plan details.

Book a demo →

When load is more than capacity: your options

This is the real job of capacity planning. It tells you whether you can accept an order and which date you can promise. It also shows where you need extra hours.

  • Run overtime or add a shift on the overloaded machine.

  • Move the operation to another machine that can do it.

  • Split the batch across two machines.

  • Send the operation out for job work (sub-contracting).

  • Agree a new date with the customer before the due date, not after.

  • If the overload repeats every month, plan for a new machine.

Common machine planning mistakes

  • Ignoring setup and changeover. Many short batches eat hours in setup alone.

  • No feedback from actual output. If actual hours never come back, the next plan repeats the same errors.

Machine planning vs capacity planning vs scheduling

They differ by time range. Long range: do you need another machine next year? Medium range: do this month's orders fit your key machines? Short range: which job runs on which machine today?

The medium-range check is called rough-cut capacity planning (RCCP). It quickly tests your master schedule against key machines before detailed scheduling. Our guide to capacity requirements planning covers the more detailed next step.

Two other plans feed the machine plan. The master production schedule (MPS) says which finished goods to make and when. Material requirement planning (MRP) works out the materials and parts the MPS needs. Machine planning checks that your machines can deliver the MPS. Read more on the master production schedule and MRP.

Scheduling itself comes in four common types:

  • Forward: start each job when the machine is free. Example: a new order starts on CNC-2 tomorrow.

  • Backward: work back from the due date. Example: dispatch on the 20th means turning ends by the 17th.

  • Infinite capacity: load jobs as if machines had no limit. Example: 12 jobs clash on the VMC on Monday.

  • Finite capacity: never load a machine past its hours. Example: the VMC is full Monday, so job 7 moves to Tuesday.

Your next step

See your machine plan next to your work orders and routing. Don't be the bottleneck. Become the AI-Run Factory.

Book a demo →

Check out other blogs

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders