What is job costing?

Job costing is a costing method that adds up the cost of one specific job, such as a single customer order or batch. It does not average costs across all production. Each job collects its own direct materials, direct labour and a share of factory overhead on a job cost sheet. Comparing that total with the price quoted tells a manufacturer the real margin on every order.

It is also called job order costing. It works best when every order is different, or when you make a batch to a customer's drawing.

What is a job in cost accounting?

A job is one piece of work you can cost on its own. It can be one customer order, one machine, or one batch of identical parts. Each job gets its own number, and every cost is booked against that number.

What do you mean by job cost?

Job cost is the total spent to finish one job. It is direct materials plus direct labour plus direct expenses plus a share of overhead.

Which factories use job costing?

Job costing suits make-to-order and batch work. Think fabrication shops, engineering goods makers, mould and die makers, machine builders and packaging runs printed to a customer's design. If two orders rarely cost the same, you need job costing.

The three cost buckets in a job

  • Direct materials: raw material and bought-out parts issued from the store for this job. The material issue slip is the source.

  • Direct labour: hours operators spend on this job, times their hourly rate. The job card or time sheet is the source.

  • Overhead: power, machine depreciation, supervision and rent. You can't trace these to one job, so you apply them at a rate.

Job-work and sub-contracting charges for one order are a direct expense; see our sub-contracting guide. Our guide to production costs breaks each bucket down further.

What are the 7 types of cost?

A common list, in factory terms:

  • Fixed: same every month (shed rent).

  • Variable: moves with output (steel, resin).

  • Semi-variable: part fixed, part variable (power bill).

  • Direct: traceable to one job (material issued).

  • Indirect: shared across jobs (supervisor's salary).

  • Sunk: spent and gone (a scrapped trial die).

  • Opportunity: profit lost by choosing another order.

How to calculate overhead for a job

The usual method is a predetermined overhead rate, set at the start of the year.

Overhead rate = estimated yearly overhead ÷ estimated yearly labour (or machine) hours

Then apply it to each job: applied overhead = hours on the job × rate.

Actual overhead will differ from what you applied. Review the gap at period end and correct next year's rate.

7 steps of job costing in a factory

  1. Open a job number for the customer order.

  2. Estimate cost from the bill of materials and routing, then quote.

  3. Issue materials from the store against the job number.

  4. Record labour hours on the job card each shift.

  5. Add direct expenses, such as job-work and sub-contracting bills.

  6. Apply overhead at your predetermined rate.

  7. Close the job and compare actual cost with the quoted price.

Why job costing breaks in Excel and registers

The method is simple. The data is the problem. Material issues sit in the store register, labour hours on paper job cards, and job-work challans in a file.

A busy shop floor fills these late, so the margin shows up only after the order ships. The next quote goes out on old numbers. Registers, Excel and WhatsApp were never built to hold cost per order.

What to check in job costing software
  • Multi-level BOM for each product

  • Work orders per customer job

  • Material issue logged against the job

  • Job-work and sub-contracting costs captured

  • Production costing for each order

  • Clean sync to Tally

How TranZact handles job costing for a manufacturer

TranZact is manufacturing AI software used by 10,000+ manufacturers. AI runs your entire operations from enquiry to dispatch.

The production module has multi-level BOM, work orders, process routing, sub-contracting and production costing. Inventory covers stock issue, and purchase covers GRN.

TranZact's AI cuts the typing that makes registers late. A photo of a paper entry becomes a system entry. Supplier invoices match to POs automatically.

Accounting stays in Tally; TranZact does not replace it. Operations run in TranZact, with a one-way sync and no double entry. See how the Tally integration works. Your overhead rate stays a decision for you and your accountant.

Production costing, multi-step BOM, routing and sub-contracting are in Grow and every higher plan, starting at ₹8,333/month billed yearly. There is no free plan; see pricing. You go live in 2–3 weeks.

Book a demo →

Job cost sheet: what goes on it

A job cost sheet is one page per job that holds every cost.

Field

What to write

Job number and customer

Unique job ID, customer name, PO reference

Quantity and dates

Units ordered, start date, close date

Direct materials

Each issue: item, quantity, rate, amount

Direct labour

Operator hours × hourly rate

Direct expenses

Job-work, sub-contracting, special tooling for this job

Overhead applied

Job hours × predetermined rate

Total and unit cost

Sum of the above; total ÷ quantity

Quoted price and margin

Price, then margin in ₹ and %

Job costing example (₹)

The numbers below are illustrative. A fabrication shop gets an order for 200 MS brackets. Its yearly overhead is estimated at ₹6,00,000 over 2,000 labour hours, so the rate is ₹300 per hour.

Cost item

Working

Amount (₹)

Direct materials

Steel and fasteners issued

48,000

Direct labour

40 hrs × ₹250

10,000

Overhead

40 hrs × ₹300

12,000

Total job cost

Sum

70,000

Cost per bracket

₹70,000 ÷ 200

350

Quoted price

As agreed

85,000

Margin

₹85,000 − ₹70,000

15,000 (17.6%)

Now add the leaks. Scrap forces a 5% re-issue of material, worth ₹2,400. One operation goes to a job worker for ₹4,000.

Total cost rises to ₹76,400, and the margin falls to ₹8,600, about 10.1%. The quote didn't change, yet over 40% of the margin is gone. The usual leaks are scrap, rework, job-work charges and an out-of-date overhead rate.

Example: where the margin went
  • ₹15,000 margin as quoted (17.6%)

  • ₹6,400 scrap re-issue plus job-work charge

  • ₹8,600 margin left (about 10.1%)

Job costing vs process costing

Job costing tracks cost per order. Process costing tracks cost per process, then divides by units made. Our guide to process costing covers it in full.

Point

Job costing

Process costing

Output

Distinct orders or batches

Identical, continuous output

Cost collected for

One job

One process for a period

Unit cost

Job cost ÷ job quantity

Process cost ÷ units produced

Fits

Fabrication, moulds, machine builders

Continuous chemical, food or polymer lines

Advantages and limits of job costing

Advantages: you see profit on every order. Your next quote rests on real cost, not a guess. Loss-making orders and customers show up early.

Limits: it needs material and time logged against each job, every shift. Done by hand, that is a lot of paperwork. Overhead allocation is also partly a judgement call.

Find the real margin on every order

Want to see job costing on your own BOMs and orders? Book a demo and walk through one recent order with our team.

Don't be the bottleneck. Become the AI-Run Factory.

Book a demo →

Check out other blogs

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders

Hero Background
Become the
AI-Run Factory

Born in India. Building for the world.

Built by IIT & IIM founders