Overall Equipment Effectiveness (OEE): Formula & Example
6 min read
By
TranZact Solutions Team
· Published


Overall equipment effectiveness (OEE) shows how much of a machine's planned production time actually makes good parts. It is calculated as Availability × Performance × Quality, or simply (good count × ideal cycle time) ÷ planned production time. 100% means only good parts, at full speed, with no stops. 85% is often called world class for discrete manufacturing, and many plants sit closer to 60%.
What OEE stands for and what it measures
OEE stands for overall equipment effectiveness. It measures one machine or line against the time you planned to run it. Three factors make up the score:
Availability counts stops: breakdowns, setups and waiting for material.
Performance counts speed: running slower than the machine's ideal rate.
Quality counts good parts: rejects and rework pull it down.
An OEE KPI is simply this score tracked over time, per machine or line. Plant heads use it to see where machine time goes, shift by shift.
The OEE formula
OEE = Availability × Performance × Quality
Availability = Run time ÷ Planned production time
Run time = Planned production time − Stop time
Performance = (Ideal cycle time × Total count) ÷ Run time
Quality = Good count ÷ Total count
Planned production time is the shift minus planned breaks, like lunch. Ideal cycle time is the fastest time to make one part. Our guide to cycle time shows how to set it.
Want to calculate overall efficiency in one step? Use the simple formula: OEE = (Good count × Ideal cycle time) ÷ Planned production time. It gives the same answer. The three-factor version tells you where the loss sits.
How to calculate OEE: a worked example for one shift
Take one shift on a sheet-metal press. The numbers are illustrative, to show the method.
Step | Working | Result |
|---|---|---|
Planned production time | 480-min shift − 30-min lunch | 450 min |
Run time | 450 − 45 min of stops | 405 min |
Availability | 405 ÷ 450 | 90.0% |
Performance | (1 min × 365 parts) ÷ 405 | 90.1% |
Quality | 355 good ÷ 365 total (10 rejects) | 97.3% |
OEE | 90.0% × 90.1% × 97.3% | 78.9% |
Cross-check with the simple formula: 355 good parts × 1 min ÷ 450 min = 78.9%. Both match. Here, stops and slow running cost about the same, and quality is the strongest factor.
Fill-in table you can copy into Excel
Put one shift per row, starting in row 2. Type the inputs and copy the formulas down.
Column | Heading | Type or formula | Example |
|---|---|---|---|
A | Planned time (min) | Type | 450 |
B | Stop time (min) | Type | 45 |
C | Run time (min) | =A2-B2 | 405 |
D | Ideal cycle time (min per part) | Type | 1 |
E | Total count | Type | 365 |
F | Rejects | Type | 10 |
G | Good count | =E2-F2 | 355 |
H | Availability | =C2/A2 | 90.0% |
I | Performance | =D2*E2/C2 | 90.1% |
J | Quality | =G2/E2 | 97.3% |
K | OEE | =H2*I2*J2 | 78.9% |
Format columns H to K as percentages. Add date and machine columns after K if you track more than one line.
How to track OEE in a small factory without sensors
You don't need machine sensors to start. Most factories already keep a shift register. Record these five numbers for each machine, every shift:
Planned production time, in minutes.
Stop minutes, each with a reason: breakdown, setup or no material.
Ideal cycle time for the part being made.
Total count of parts made.
Rejects, including start-up scrap.
The operator notes stops and counts. The shift supervisor checks them and enters them before the shift ends. Rejects come from whoever inspects the parts.
Review the trend once a week. Pick the lowest of the three factors and the stop reason behind it. Fix that one loss before chasing the rest.
A simple weekly OEE routine
Start with your bottleneck machine
Record five numbers every shift
Calculate OEE in the Excel sheet
Review the trend each week
Fix the lowest factor first
Where TranZact fits
OEE is only as good as the records behind it. When output sits in a register, rejects on WhatsApp and the plan in Excel, the numbers rarely match. Someone ends up rebuilding them every week.
TranZact is manufacturing AI software used by 10,000+ manufacturers. It keeps the production, rejection and machine-plan records an OEE calculation needs:
Output by job: production management with work orders, process routing and multi-level BOMs.
Rejects: quality control for raw material and finished goods, on the Dominate plan.
Machine plan: machine planning, also on the Dominate plan.
Reports: 65+ reports on every plan, plus real-time MIS on Dominate.
Your OEE sheet: Excel and Google Sheets integration.
A clear limit: TranZact is not a sensor-based machine-monitoring tool. Stop minutes still come from your shift register. Ask in the demo how to set up an OEE view for your lines.
See what each plan includes on our pricing page. You go live in 2–3 weeks.
What is a good OEE score?
100%: perfect. Only good parts, at full speed, with no stops.
85%: world class for discrete manufacturing.
60%: fairly typical.
40%: common when a plant first starts measuring.
The 85% mark breaks down as 90% Availability × 95% Performance × 99% Quality. So is 90% OEE good? Yes, it is above the world-class mark for discrete work. First check that stops and the ideal cycle time are recorded honestly.
There is no single ideal score. A line with frequent changeovers and many products will reasonably score lower. The 85% mark also doesn't apply to process manufacturing. Compare each machine with its own past numbers.
The six big losses behind a low OEE
Lost OEE comes from six losses, two for each factor.
Loss | Factor hit | Factory example | First fix |
|---|---|---|---|
Equipment breakdowns | Availability | Press motor fails mid-shift | Preventive service on critical machines |
Setup and adjustments | Availability | Mould change on a moulding machine | Ready the next mould before the stop |
Minor stops | Performance | Jammed feeder on a packing line | Log short stops with a reason |
Reduced speed | Performance | CNC slowed for a worn tool | Check speed against ideal cycle time |
Start-up rejects | Quality | First parts after a die change scrapped | Fixed start-up settings per job |
Production rejects | Quality | Burrs on auto parts mid-run | Inspect where the defect starts |
Our guide to breakdown maintenance covers how to cut machine stops. For rejects, place checks at the right step with a quality inspection plan.
OEE vs production efficiency
Production efficiency compares what you made with what you should have made. The formula is Production efficiency = (Actual output ÷ Standard output) × 100. If the standard is 400 parts and you made 360, efficiency is 90%.
OEE is stricter. It measures against all planned time, so stops count against you. It also counts only good parts. Our guide to production rate covers output per hour.
Production efficiency vs OEE at a glance
Production efficiency | OEE | |
|---|---|---|
Compared against | Standard output | Planned production time |
Counts stops | No | Yes, as Availability |
Counts slow running | Yes | Yes, as Performance |
Counts rejects | No | Yes, as Quality |
Shows where loss sits | No | Yes, by factor |
Start with one machine this week
Pick the machine that limits your output and fill in the sheet for five shifts. The lowest factor shows you where to start. Then see how TranZact keeps the job, reject and machine records behind your OEE.